Item No. 4 - Wadsworth Boulevard Improvement Project

Motion to amend the contract for Engineering Consulting Services for Phase II of the Wadsworth Boulevard Improvement Project with HDR Engineering, Inc., Denver, CO, to incorporate additional design fees in the amount of $384,627 for a total project cost of $2,529,557.12
This is a recording of the July 13, 2020 City Council meeting. 

Files

Council Action Form ( 0.99 MB )

Comments & Feedback

Comments
 
This case is closed, online commenting is no longer available.
Online comments closed at 12:30 PM MDT 7/13/20.
Do NOT continue with the city's widening of Wadsworth. Not during COVID and NOT disrupting the City and the Businesses along Wadsworth as they are already decimated with the downturn of pandemic loss of business.
July 13, 2020, 11:38 AM
VIVIAN VOS