Item No. 9 - RESO - amend CDOT contract for Improve Wads
The original completion date for the Improve Wadsworth Project was established in the original contract between the city and the Colorado Department of Transportation (CDOT) as October 25, 2025. Construction is currently on-going with substantial completion expected by the end of 2025. Final completion is expected in the spring of 2026. As the project will not be complete by the contract date, it is necessary to extend the contract completion date to October 25, 2030 to ensure that adequate time is provided for project closeout.