City Council Meeting
City Council Meeting
8 items Mon, Feb 27, 2023 at 6:30pm
 Approved
∙ Approved 8 to 0
∙ Agenda item 8 of 8
Item No. 7 - Motion to approve cont. amend. w/Concrete Works
Staff recommends approval of a contract amendment with Concrete Works of Colorado, Inc. to complete Phase IIA of the Improve Wadsworth Project. Concrete Works is completing the initial phase of work in the corridor. The cost of the Phase IIA contract amendment is $11,894,015.87 which includes the cost of the roadway work, water-related improvements, and a $750,000 contingency for unexpected items. Staff is working with the Colorado Department of Transportation (CDOT) to acquire their concurrence on this contract amendment. Therefore, this action is subject to CDOT approval.

Files

Item No. 7 - Motion to approve contract amend. with Concrete Works ( 4.72 MB )
Public Comments
Comments are not being accepted on this item.